This page may be viewed in: English
The cleanup of the Lower Duwamish Waterway (LDW) is a several hundred-million-dollar effort that takes time and needs to be done right. Once complete, the cleanup of contaminated sediment and pollution source control is anticipated to reduce over 90 percent of the waterway’s PCB sediment contamination. Our scientists are gathering data about the contamination and our engineers will be using this data to ensure the design meets EPA’s cleanup plan requirements.
We are planning ahead for cleanup construction | Cleanup design for the Lower Duwamish Waterway | LDWG Statement on the EPA’s Updated cPAH Standard | Controlling Sources of Contamination
Draft Community Impacts Mitigation Plan Now Available
The members of the Lower Duwamish Waterway Group (LDWG) released the Community Impacts Mitigation Plan (CIMP) in July 2024.
This plan was developed as an extension of the Community Outreach and Communications Plan. The CIMP addresses community concerns related to upper reach cleanup construction, builds upon feedback gathered through engagement with Duwamish Valley communities, and outlines strategies to manage potential impacts.
- Read the full CIMP.
- Read the summary.
El Community Impacts Mitigation Plan ya está disponible.
- Lea el plan completo.
- Lea un resumen del plan.
Kế Hoạch Giảm Thiểu Tác Động Đến Cộng Đồng hiện đã được công bố.
- Đọc toàn bộ kế hoạch.
- Đọc bản tóm tắt kế hoạch.
សេចក្តីព្រាងស្ដីពីផែនការកាត់បន្ថយផលប៉ះពាល់សហគមន៍ឥឡូវនេះមានហើយ។
We are planning ahead for cleanup construction
EPA and the members of LDWG anticipate that cleanup construction of the Lower Duwamish Waterway will begin in Fall 2024.
Construction activities for the sediment cleanup will begin in the upper reach (the southernmost two miles of the Superfund site, between Duwamish Waterway Park and the South 102nd Street bridge) and will continue towards the south end of Harbor Island over the next decade.
We will use a few methods to clean up the waterway sediment, including dredging, capping, natural and enhanced recovery processes. Learn more about how we clean up the river.
Read the latest information about construction plans on the Construction News page.
Cleanup design for the Lower Duwamish Waterway
The Lower Duwamish Waterway has been divided into three segments to help implement EPA’s cleanup plan. We call these the upper, middle, and lower reaches. Each section will have its own design and cleanup schedule. Cleanup will begin upstream (south) in the upper reach and move downstream. The members of LDWG are currently designing the cleanups of the upper and middle reaches in support of the EPA-led cleanup plan.
The first step in the design process is to conduct pre-design investigations – in this step, scientists and engineers gather more data about contamination and site conditions in the waterway. Engineers use these data to define which areas need cleanup and decide which cleanup technologies can be used to meet EPA’s cleanup plan requirements in specific locations.
The design goes through three stages before it is finalized: 30%, 60%, and 90%. Each stage provides more information and detail about the design. EPA oversees all steps of the design process and will lead public involvement and engagement through their Roundtable and Stakeholder meetings during the pre-design and design phases to set the final cleanup design.
A Seat at the Table
EPA has convened a “Roundtable” to help affected communities and local agencies work together to mitigate the impacts of cleanup. The Roundtable brings together governments (federal, tribal, state, and local) and other stakeholders (e.g., residents, businesses, industries, labor, neighborhood groups, waterway users, fishers, and others) to share information and make recommendations during the design and implementation of the cleanup plan.
Upper Reach Cleanup Design
In 2020 and 2021, scientists and engineers completed two phases of pre-design investigation work for the upper reach. We completed the 30% Remedial Design in 2022 and in February 2023, submitted the 60% design to EPA. In December 2022, we collected additional investigation samples and used that data to inform our 90% Remedial Design. We submitted 90% Remedial Design to EPA in July 2023 and completed the final design for the cleanup in January 2024. Remedial design for the upper reach cleanup is now complete and ready for the next phase of work: cleanup construction.
Middle Reach Cleanup Design
The design process for the middle reach of the Lower Duwamish Waterway is underway. We began collecting sediment samples as part of pre-design investigation work in December 2022. The pre-design investigation work will continue through 2024. We expect to finish the cleanup design for the middle reach in 2027.
Cleanup Construction Schedule for the First Two Reaches
Cleanup construction in the upper and middle reaches of the Lower Duwamish River is expected to begin in late 2024 and late 2027, respectively.
Upper Reach Remedial Design Timeline
Timeline graphic below shows:
- Remedial design planning—January 2019 through Quarter 1 2020
- Three phases of predesign investigation:
- Phase 1: Define cleanup areas—Quarter 2 2020 through Quarter 1 2021
- Phase 2: Refine cleanup areas and collect engineering data—Quarter 2 2021 through early 2022
- Phase 3: Fill remaining data gaps if needed—Quarter 2 2022 through Quarter 1 2023
- Four phases of remedial design:
- 30%—Quarter 4 2021 through Quarter 1 2022
- 60%—Quarter 2 2022 through Quarter 4 2022
- 90%— Quarter 1 2023 through Quarter 2 2023
- 100%— Quarter 3 2023 through Quarter 4 2023
- Construction contracting and work plans— Quarter 1 2024 through Quarter 3 2024
- Construction start goal—Quarter 4 2024
Middle Reach Remedial Design Timeline
Summer 2020, LDWG and its contractors collected samples of sediment to test for contaminants of concern. This information contributed to the remedial design.
Controlling Sources of Contamination
The members of LDWG work together with EPA and Ecology to keep new and ongoing sources of pollution out of the river.
Contaminants in soil and groundwater on sites around the river can find their way into the river through storm runoff, spills and leaks, industrial discharge, erosion and leaching, and other pathways. Ecology is leading efforts to control sources of contamination from areas upland of the waterway, and EPA is leading efforts to clean up the river sediments. The long-term goal is to minimize re-contamination of the river sediment and restore the river’s water quality.
King County and the City of Seattle have helped hundreds of individual businesses and property owners address problems with hazardous materials, industrial wastewater, stormwater, spill containment, and leaking pipes. LDWG members are also working with agencies to improve the health of the Green/Duwamish watershed, restore natural resources, and further protect fish and wildlife habitat. King County and the City of Seattle are working toward improved water quality with large investments in controlling combined sewer overflows and improving stormwater quality.